Illustrative image – not actual.Vijayawada in Andhra Pradesh which is getting its first storm water drainage system is facing hurdles. So far, only 57 percent work has been completed on the project. A network of merely 250 km had been set up as against a target of 443 km.
The project is being implemented at a cost of Rs 461 crore. Out of the 301 km of targeted length of minor drains only 198 km drains had been laid and out of 142 km major drains only 52 km drains had been laid.
At present, only 250 to 400 mtr of drains were being laid per day as against the expected 1,000 mtr per day.