The Andhra Pradesh Government plans to add 6,279 MW of capacity to the grid from APGENCO, central generation stations and private sector by March 2014.
Around Rs 20,000 crore is being invested in the transmission and distribution sectors over the next four years to enhance transmission and distribution infrastructure. Orders have been finalised for supply of 880 MW under medium-term bidding for the period from June 2013 to May 2016. Also, the state government has sought allocation of power from the Central Government’s unallocated share from Central Generating Stations of Southern Region up to 500 MW. It has approached the Central Government to allocate power from unallocated power of 300 MW from the Kudankulam Atomic Power Plant and 75 MW from the second stage of Neyveli Lignite Corporation, both in Tamil Nadu, to the state.
PGCIL has taken up construction of 765 kV substations and lines for connecting the southern grid with the new grid. The works are slated to be completed by January 2014 helping in and additional flow of power from the new grid to the southern grid.