Illustrative image – not actual.The Andhra Pradesh Government has allocated a 360 MW Pumped Storage Hydro Power (PSP) project at Koppolu in YSR district to Chinta Green Energy under the state's Integrated Clean Energy Policy, 2024.
In a major development, the project’s capacity has been expanded from the original 360 MW to 2,400 MW, highlighting the state’s focus on large-scale energy storage infrastructure. The project will utilise the existing Gandikota Reservoir as its lower reservoir, pending approval from the Water Resources Department (WRD). The proposal requires the allocation of 38.00 MCM of water for one-time filling and 2.79 MCM annually to offset evaporation losses, with water use subject to availability and regulatory guidelines.
As part of the regulatory process, the allocation of water from the Gandikota Reservoir will be allowed only after meeting irrigation and priority allocations. To reduce future strain on the reservoir, the developer will need to set up an independent lower reservoir.