Illustrative image – not actual.
NTPC will use the land on a long lease basis of 33 years to set up the 4,000 MW power project in Pudimadaka village of Atchuthapuram Mandal, Visakhapatnam, with a total investment of Rs 20,000 crore.
The company will complete this project before March 2019.
This land is close to NTPC’s existing Simdhari power project and makes it feasible for the new project. It allows utilising the existing infrastructure such as housing facility, railway siding and technical manpower already present in Vizag.
After completion, it will be the biggest single location power project in Andhra Pradesh.