The Andhra Pradesh Cabinet has formally approved to revise the the power purchase agreement (PPA) signed with BPL Power for developing the coal-based plant at Ramagundam in Karimnagar district.

The Cabinet has permitted the company to increase the capacity from 2x260 MW to 2x300 MW with a cap on per megawatt cost of Rs.4.76 crore.

Earlier in 2004, the government had terminated the PPA since the company had failed to achieve financial closure and transferred the same project to AP Genco. However, later the company approached the courts for the revival of the project.