Andhra Pradesh Cabinet approves Pranahita water supply projectIllustrative image – not actual.

The Andhra Pradesh Cabinet on, 24 September 2008, approved a Pranahita water supply project, which will be implemented in phases.

Under Phase I, Hyderabad Metropolitan Water Supply & Sewerage Board (HMWS&SB) will tap 10 tmcft of Godavari water to meet the needs of Greater Hyderabad and its surrounding areas. The estimated cost of the first phase is likely to be around Rs.3,375 crore, of which the state government's share will be Rs.1,232.85 crore, GHMC's share Rs.960.90 crore and that of the Central Government will be Rs.1181.25 crore.

Work on the first phase is likely to commence by November 2008 and is scheduled for completion within 30 months. The Water & Power Consultancy Services (WAPCOS) is entrusted with the feasibility study of diverting Godavari waters to meet the future.

 