Illustrative image – not actual.Andheri-Ghatkopar Link Road (AGLR), undertaken by the Mumbai Metropolitan Region Development Authority (MMRDA), is likely to be completed by December 2014.
Construction of the six km AGLR has only been completed from Andheri to Jagruti Nagar, so far. Work on the remaining 1.5 km stretch has been delayed due to the ongoing Versova-Andheri-Ghatkopar (VAG) metro project work.
The project involves widening and strengthening of the Andheri-Ghatkopar Link Road stretching from Western Express Highway to Sakinaka (Eastern Express Highway).
At first, the Public Works Department had undertaken construction of the Andheri-Ghatkopar Link Road, but could not complete it. Later, the Mumbai Metropolitan Region Development Authority (MMRDA) decided to complete the work.
After completion of the civil construction of the metro project, MMRDA will be ready to complete the 1.5 km link between Jagruti Nagar and LBS Road.
After completing the AGLR project, the Link Road will open at Shreyas Cinema Corner which will directly connect both the express highways.