Illustrative image – not actual.Construction of Bihar’s first access-controlled greenfield expressway, the Amas-Darbhanga Expressway, is progressing rapidly, with around 30 percent of the project completed and the entire 189-km corridor targeted for completion by December 2026.
Developed by the National Highways Authority of India (NHAI) under the hybrid annuity model (HAM), the four-lane expressway will connect Amas in Gaya to Shivrampur in Darbhanga, improving connectivity between North and South Bihar through Mithilanchal. The project, estimated at around Rs 5,000 crore, is being constructed as a new alignment across agricultural land and fields rather than through widening of existing roads. Construction activities are underway simultaneously across all four packages to meet the revised timeline. In Patna, the corridor will connect through the Kacchi Dargah-Bidupur six-lane bridge over the Ganga River. The Vaishali-Samastipur stretch has achieved around 24 percent completion, while the Samastipur-Darbhanga package has crossed nearly 34 percent.
According to an NHAI official, “To meet the deadline, the project has been divided into four packages and work is running simultaneously. Package-1, covering around 55 km from Amas to Jehanabad, has completed around 31% of construction work. Major work on roadbed and structures is in progress. Around 31% work on the 54-km-long Jehanabad to Vaishali stretch has also been completed. Construction of carriageways and bridges continues.”