Illustrative image – not actual.Karnataka
Power Corporation Ltd (KPCL) has decided to implement the 297 MW Almatti Power
Project through the Independent Power Producer (IPP) route. This has been done
with a view to keeping the minimum rate of return on equity to at least 16 per
cent.
As per the earlier scheme, KPCL would
have to underwrite the entire project cost of Rs.715 crore. Under the new
proposal, the project cost would be shared by another public sector entity,
Krishna Bhagya Jala Nigam Ltd (KBJNL). The debt equity ratio of the project is
7:3 which would mean that the equity of Rs.214.50 crore would have to brought
in equally by KPCL and KBJNL. The remaining Rs.500.5 crore of debt would be
sourced through financial institutions.
The transformation of this power project
from a State-owned project to an IPP also has a favourable impact on the State
government since the need for providing for contingent liabilities (in the form
of guarantees) is obviated.