Illustrative image – not actual.The 15 MW First Unit of 290 MW Rs.674.4 crore Almatti Dam Hydel Power Project is expected to be commissioned ahead of schedule by December 2003 as against the earlier scheduled March 2004. The entire project involving setting up of six units (1 x 15 MW + 5 x 55 MW) is slated to be completed by July 2005.
Bharat Heavy Electricals (BHEL) has already started erection of equipment for the first unit. Work was in progress on the other five units. Karnataka Power Corporation (KPCL) has completed concreting of extended draft tube area upto 488.4 metres including the pier portion and second stage concreting around the draft tube gate groove lines for the first unit was in progress.