Illustrative image – not actual.The 8 highway stretches taken up under the annuity method, in the first phase of the National Highways Development Project (NHDP), have achieved financial closure.
Of the entire Rs.58,000 crore NHDP project, 8 sections have been awarded to various consortiums under the annuity method. Many public sector banks and financial institutions like Federal Bank, UCO Bank, J&K Bank, UBI and Canara Bank have come forward to fund these projects.
Details about the 8 annuity based projects that have achieved financial closure are given below:
|
Sr.
No. |
Projects |
States |
Executing
Company |
Lenders |
Cost
(Rs.cr) |
|
1 |
Belgaum-Maharashtra Border section NH-4 (77 km) |
Karnataka, Andhra Pradesh |
Punj Lloyd, IL&FS, CTNL |
Consortium of 12 leading financial institutions |
525 |
|
2 |
Panagarh-Palsit NH-2 Road (64 km) |
West Bengal |
Gamuda, WCT Engineering |
IDFC-led consortium |
400 |
|
3 |
Dharmavaram-Tuni NH-5 Road (46 km) |
Andhra Pradesh |
Punj Lloyd, Gamnon India |
ICICI-led consortium |
295 |
|
4 |
Rajahmundry-Dharmavaram NH-5 Road (54 km) |
Andhra Pradesh |
Punj Lloyd, Gamon India |
ICICI-led consortium |
293 |
|
5 |
Tuni-Anakapalli NH-5 Road (60 km) |
Andhra Pradesh |
GMR Tuni-Anakapalli Expressways |
ICICI-led consortium |
312 |
|
6 |
Tambaram-Chingleput -Tindivanam NH-45 Road (93 km) |
Tamil Nadu |
GMR Tambaram-Tindivanam Expressways |
ICICI-led consortium |
377 |
|
7 |
Palsit-Dankuni NH-2 (DurgapurExpressway) Road (69 km) |
West Bengal |
Gamuda, WCT Engineering |
- |
654 |
|
8 |
Nellore Bypass NH-5 Road (17 km) |
Andhra Pradesh |
NYSE Infrastructure |
- |
157 |