Illustrative image – not actual.Gujarat Mineral Development Corporation's (GMDC) 250 MW Akrimota power project is advancing as per schedule and is expected to be completed by September 2003. This was stated by GMDC’s chairman, Mr Mukeshbhai Zaveri, at the annual general meeting, held on 28 September 2001.
Mr Zaveri stated that all power purchase agreements
with the Gujarat Electricity Board had been executed and all contracts for
necessary works had also been issued. In fact, work such as preparing boilers,
chimneys, turbines, etc. were in progress.
Till date, the corporation had invested a total of
Rs.195 crore on the power project. Financial institutions and banks had agreed
to sanction Rs.1,400 crore for the project against the required Rs.1,120 crore.
Mr Zaveri stated that the 125 MW first unit of the
power project will be operational by March 2003, while the second unit would be
operational by September 2003.