Illustrative image – not actual.The Airports Authority of India is unlikely to open the revamped Chennai airport by mid-April due to lack of power supply.
The airport may get power supply soon. However, at least a month is required for trials and testing before the airport is actually inaugurated. Therefore, the AAI may have to delay the airport inauguration by a week or so. Currently, the Tamil Nadu Electricity Board is working on it and line installation is underway. The power requirement at the expanded airport is around 110 kVa.
The Rs 2,015-crore expansion of the Chennai airport envisaged construction of a new domestic terminal, expansion of international terminal by 59,300 sq mtrs and the extension of secondary runway (which is currently 2.07 km long) by 1.03 km.