The department of expenditure and the Union ministry of health and family welfare have approved the hike in the project cost of AIIMS, Madurai. The hospital project will now cost Rs 1,978 crore. The original cost estimated in 2018 was Rs 1,264 crore.
The central government clarified that the project implementation was delayed since the project was to be taken up under EBR (External Benchmark Rate) Funding through Japan International Cooperation Agency (JICA). The loan agreement was signed between the governments of Japan and India in March last year.
The project cost was revised at Rs 1,978 crore by JICA following the inclusion of 150 bedded Infectious Disease Block and some other additions.
The project would be implemented in five years and eight months i.e. from March 2021 to October 2026. The state government has handed over the required land to the Union government in February 2020.