Illustrative image – not actual.Ahmedabad Municipal Corporation (AMP) plans to develop a 20-km long stretch of Bus Rapid Transit System (BRTS) in the eastern part of the city in Gujarat. The project is estimated to cost Rs 103.58 crore.
The proposal to award the Rs 116.74 crore contract, at 12.71 per cent higher rate than what was estimated, is likely to be placed before the AMC's standing committee shortly.
The 20-km long stretch includes stretches from Shahalam to Odhav via ST and Soni Ni Chawl, from Kalupur Approach to Naroda Village via Amdupura, Memco, Naroda Patia and from Vivekanand approach to ST via Astodia. The stretch is part of the first package of the Phase II of Janmarg Project.
As per the tender price, AMC is likely to spend nearly Rs 5.84 crore for development of BRTS corridor in the eastern part of Ahmedabad. This price does not include cost of building bus shelters, garden development, installation of high mast lights and other beautification elements.
AMC has set the 21 months time limit to complete the project, while defect liability period has been fixed at 60 month.