Ahmedabad metro route change to cost Rs 500 crIllustrative image – not actual.
The new route of the Ahmedabad metro Phase-I is likely to lead to an additional cost of Rs 500 crore.


Two more stations have been added on the north-south corridor of the Phase-I metro route. As per the change, the route connecting the APMC in South to Motera (north-south corridor) has been tweaked and aligned with the Botad-Sabarmati meter gauge line after the Indian Railways agreed to allow the metro project to use its land.


The old north-south route that connected APMC-Vasna-Anjali-Paldi-Madalpur-Nava Gandhigram-Ashram Road-Usmanpura-Ranip has been done away with and a new route connecting APMC-Jivraj Park-Rajiv Nagar-Shreyas-Parimal-Gandhigram-Income Tax-Usmanpura-Vijay Nagar-Vadaj-Ranip has been introduced.


With this, the total length of Phase-I stands increased from the earlier 35.96 km to 37.76 km.


The Ahmedabad - Gandhinagar Metro Rail Project was conceived in 2003 and the first Detailed Project Report for the Ahmedabad metro project was drawn up by the Delhi Metro Rail Corporation in 2005. The route of the project has so far been changed four times since then.


Though the project is still in the planning stage, state government figures indicate that Rs 565.60 crore has already been invested in the last two years till 31 May, 2014.


The Rs 10,700 crore Phase-I of the metro project will comprise the following two corridors:
North-South Corridor (APMC to Motera stadium: 17.23 km): APMC-Jivraj-Rajiv Nagar-Shreyas-Parimal-Gandhigram-Income Tax-Usmanpura-Vijay Nagar-Vadaj-Ranip-Sabarmati Railway Station-AEC-Sabarmati-Motera Stadium.


East-West Corridor (Thaltej Gam to Vastral Gam: 20:53 km): Thaltej Gam-Thaltej-Doordarshan Kendra-Gurukul Road-Gujarat University-Commerce Six Roads-Stadium- Shapur-Gheekanta-Kalupur Railway Station-Kankaria East-Apparel Park-Amraiwadi-Rabari Colony-Vastral-Nirant Cross roads-Vastral Gam.

 