The construction work on the Agra Metro Rail project in Uttar Pradesh is progressing at a fast pace. The momentum has been maintained largely due to extensive arrangements made for prompt medical care to the large work force at the sites.
Groups of 15 have been formed to work in a coordinated manner, avoiding proximity. In a record five month period 400 piles have been completed.
Of the total 686 piles, 400 for the three km elevated section of priority corridor from Taj East Gate to Jama Masjid, have been completed till date. Along with this, 45 pile caps and 16 piers have also been completed for this section from Taj East Gate to Fatehabad road.
The Agra Metro Project's civil construction work is going on for priority section of the first corridor, which runs from Taj East Gate to Sikandara. The priority section is a six km stretch from Taj East Gate to Jama Masjid, which comprises three km elevated and three km underground section.