Agartala-Udaipur road upgradation to be completed by 2019 endIllustrative image – not actual.
National Highways and Infrastructure Development Corporation (NHIDCL) has taken up two-laning with paved shoulder of Agartala-Udaipur section from 6.80 km to 55 km of NH-44 in Tripura on EPC basis.

Pre-qualification bids were invited from contractors to execute the project in January 2014 and KMC Construction bagged the order for improvement of the road project in October 2014.

KMC Constructions signed agreement to implement the project in March 2015 and following this Union Minister of Road Transport and Highway Nitin Gadkari laid the foundation stone on 30 June 2015.

Soon work on the project commenced. Around 58 percent of the project work was completed as of 30 June 2018

The estimated cost of the project is worth Rs 749.29 crore. As per the latest update available with Projects Today, 82 percent of the project work has been completed. The entire project is expected to be completed December 2019.