The National High Speed Rail Corporation (NHSRCL), which is implementing India's first bullet train project, has awarded a Rs 6,397 crore contract to Afcons Infrastructure, for constructing a 21-km-long tunnel.
As per tender, Afcons will undertake the construction of a twin track under the sea rail tunnel of seven km at Thane Creek in Maharashtra, and three tunnel boring machines and new Austrian tunnelling method will be utilised for the construction work.
Technical bids of this tender were opened in February, 2023 and financial bids were opened during April 2023.
The Ministry of Railways is pursuing the goal to run the bullet train on a larger section in 2027. The maximum speed will be 320 kmph, and the total length of the corridor stands at 508 km spread over 12 stations between Mumbai and Sabarmati.