AECOM India has won the general consultant (GC) service contract for civil works of Mumbai Metro‘s upcoming 9.20 km Line-10 (Gaimukh-Shivaji Chowk in Mira Road) and 20.7 km Line-12 (Kalyan-Taloja).
AECOM India’s selection among five bidders was made on the quality-cum- cost basis system (QCBS) method in which the winner’s selection is made through a combination of points scored in technical and financial evaluation.
In this, AECOM India had recorded the highest technical score and also placed the lowest financial bid.
The Mumbai Metropolitan Region Development Authority (MMRDA) had invited GC bids in July 2020 with a 48-month completion period. Technical bids were opened in October 2020 to reveal five bidders.
Mumbai Metro’s Line-10 will be built as a western extension of the 35.2 km Line-4/4A (Green Line) with four stations at Gaimukh Reti Bundar, Varsova Char Phata, Kashimira, Shivaji Chowk. The line will form an interchange with Line-9 (Red Line) at Pandurang Wadi, where possibly a fifth station could come up for providing easy transfers.
Line-12 will be built as a 20.75 km southern extension of the 24.95 km Line-5 (Orange Line) with 17 stations at Ganesh Nagar, Pisvali Gaon, Golavali, Dombivli MIDC, Sagaon, Sonarpada, Manpada, Hedutane, Kolegaon, Nilaje Gaon, Vadavali, Bale, Waklan, Turbhe, Pisarve Depot, Pisarve, Taloja. The line’s depot is planned at Pisarve.
The foundation stone for both lines was laid by Prime Minister Narendra Modi in September 2019. With this development, civil tendering for Line-10’s construction can be expected to start in 2021 if the state government and MMRDA have financial appetite.
The development of Line-12 is possible independently without Line-5, which is facing major land acquisition hurdles in Kalyan, but ultimately its success and integration with the rest of the network is dependent on Line-5.