Illustrative image – not actual.The Asian Development Bank and the Himachal Pradesh government, on 10 November 2008, entered into an agreement under which the bank sanctioned a loan of $800 million to strengthen its hydropower potential. The loan has been sanctioned under Himachal Pradesh Clean Energy Development Investment Programme.
The loan package will help finance the construction of four medium to large run-of-river hydropower generating plants that will bring in combined capacity of 808 MW for the state. The projects identified include the Sawra-Kuddu hydroelectric project (111 MW) in Shimla district, Stage I, II and III of Kashang project (195 MW) in Kinnaur district, and Shongtong-Karchham project (402 MW) in Kinnaur.
The total estimated cost of these projects is $1.5 billion, out of which ADB has financed $800 million in the form of a multi-tranche financing facility. The loan has a 25-year repayment period.
Also See:
ADB approves loan to expand hydropower generation in Himachal (24-Oct-08)