Illustrative image – not actual.The West Bengal State Government is planning to seek financial assistance from Asian Development Bank (ADB) for West Bengal Power Development Corporation’s proposed 2,000 MW thermal power project at Sagardighi in Murshidabad district of the State. This was state in the budgetary speech, of the State Power Minister, Mr Mrinal Banerjee. Reportedly, the State government has already approached ADB in this regard.
The Minister also stated that the legal hurdles
regarding the award of the civil contract for the 900 MW Purulia Pumped Storage
Project had been resolved and the project would be commissioned by 2005-06.
Among the other steps that the State government planned
to take in the power sector during 2001-02, was providing quality power to the
consumers through better transmission and distribution. In this connection, a
Rs.860 crore project was being implemented with assistance from Japan Bank for
International Co-operation. This project involved setting up of new
substations, installation of transformers and drawing of new lines, and would
be completed by March 2002.
The State Government also planned to achieve 100 per
cent metering of all consumers by December 2001.