ADB approves Rs.4,500 crore for rail projectsIllustrative image – not actual.

Asian Development Bank has approved the funding for strengthening the rail network along the Golden Quadrilateral.

 

ADB would finance Rs.4500 crore of Rs.8000 crore required for executing the projects. The railways would bring in Rs.1500 crore and Rs.2000 crore is to be raised from the market.

 

The projects to be funded by ADB are:

  • Third line between Ghaziabad and Aligarh costing Rs.238 crore.
  • Raichur – Guntakal doubling involving an investment of Rs.136 crore.
  • Cuttack – Barang doubling at a cost of Rs.127 crore.
  • Khurda – Barang third line costing Rs.133 crore.
  • A new terminal to be constructed at Anand Vihar in Delhi at a cost of Rs.83 crore.

 

The projects under consideration for funding are:

  • Daund – Gulbarga doubling at a cost of Rs.502 crore.
  • Delhi – Palwal fourth line with an investment of Rs.210 crore.
  • Thiruvallur – Arakonnam fourth line costing Rs.75 crore.
  • Third line between Palwal – Mathura to cost Rs.240 crore.

 

The ADB loan carries a 20-year tenure at the rate of 60 basis points over six month Libor with a five year moratorium period. These projects are to be executed by the Rail Vikas Nigam.