Adani Power to import coal for Mundra plantIllustrative image – not actual.

Adani Power is likely to import more than 50 per cent of the coal requirement for its 4,620 MW Mundra plant from Indonesia, though the company has tied up for domestic linkages.

The total coal requirement for the plant is 15 million tpa, and around eight-nine million tpa of coal is to be imported. The company has long-term supply agreements and mining rights in the Bunyu Island of Indonesia.

Adani Power is planning a Rs 2,200 crore initial public offer to part-fund its Phase IV of Mundra plant of 1,980 MW and for a similar capacity plant at Tiroda in Maharashtra. The company has been tied up land, coal and water linkages for the Mundra and Tiroda projects. It has also tied up with the State utilities for about 70 per cent of the 6,600 MW to be produced at the two projects. The balance will be traded on merchant basis.

The company has set up 433 circuit km of 400 kV line to connect the power station to Dehgam, the Gandhinagar sub-station of PGCIL, to evacuate power in the first three phases of the Mundra project. In the fourth phase, an 800 km HVDC line will link the power station to Mohindergarh, Haryana. The Tiroda plant will have a 140 km line to Koradi and another 225 km line to Wardha.

Also See:

Adani Power's Tiroda project may face land acquisition problems (20-Jul-09)