Illustrative image – not actual.Adani Power has reportedly decided to expand capacity at the under-construction 1,980 MW thermal power project in Tiroda, Maharashtra, to 3,300 MW.
The change in scope of capacity envisages a total investment of nearly Rs 14,000 crore.
The project is being implemented by Adani Power Maharashtra, a subsidiary of the company. The power plant is expected to use coal from captive mines at Lohara (West) and Lohara extension coalfields. The company expects to generate power from Tiroda by end-2010.
Also See:
Adani, MMTC in fray to supply coal to GSECL (23-Oct-09)