Adani Ports commences trial run at Vizag coal terminalIllustrative image – not actual.
Adani Vizag Coal Terminal, a subsidiary of Adani Ports and special economic zone (APSEZ), has successfully commenced the pre-commissioning trial of its coal terminal at Visakhapatnam Port. The coal import terminal has a capacity of 6.5 million tpa.


The trial run started on 14 July 2014, by lightening Indonesian steam coal from M.V. Galveston and will continue till the unloading of 50,000 tonne in the berth.


The arrival of a vessel and launching of cargo handling on a trial basis is a precursor to undertaking commercial operations of a terminal.


The Vizag coal terminal was set up with an investment of Rs 400 crore and was completed in December 2013, eight months ahead of schedule. It has the capacity to handle 27,000 tonne per hour, with harbour mobile cranes of 100 tonne capacity, ultra modern wagon loaders and 2.1 km long conveyor system.


Adani Ports recently signed an agreement with France’s CMA CGM Group to develop a new common user container terminal at Mundra Port.