Illustrative image – not actual.ACME has announced the commissioning of its 100 MW solar plant in the state of Rajasthan.
The plant has five units of 20 MW each and is a National Solar Mission Phase-II project, which has been set up near Jodhpur, Rajasthan. ACME has commissioned the solar plant within 150 days of laying the foundation stone.
The power generated from the project will be evacuated through a 132 kV line linked to the project site. Under the power purchase agreement signed with the Solar Energy Corporation of India, the solar power producer will supply electricity to Rajasthan.
In addition, ACME has a 25 MW plant in Madhya Pradesh and has generated 25 GWh within six months of installation.