ACC’s projects on trackIllustrative image – not actual.

ACC is moving ahead swiftly with its expansion drive.

Work on a new line of three million tpa of cement at Chanda in Maharashtra along with a 25 MW captive power plant is on track and is slated to be completed by third quarter of current fiscal.

The company is executing three projects viz. a residential township at its plant in Kudithini, Karnataka; central control room in the upcoming Chanda project and a hostel in the training establishment of Thane Complex.

Meanwhile, the company's Bargarh expansion project in Orissa has been completed in April-June quarter of 2010, increasing the plant's installed capacity to 2.1 million tpa. ACC commissioned a wind energy farm in March 2010 near Satara in Maharashtra set up with two turbines of 1.25 MW capacity each.