Illustrative image – not actual.ACC has drawn up plans to increase the cement capacity of its various plants. The company is mulling over part financing the expansion by raising Rs.300 crore through FCCB route or GDR issues.
The company plans to increase its plant capacity at following locations:
- Chaibasa unit: The unit would be converted into a dry process facility with an enhanced capacity of 1.5 million tpa. The expansion will cost Rs.250 crore.
- Idcol's plant: The company has recently acquired 86.2 per cent stake in Idcol Cement. ACC plans to increase Idcol's clinker capacity at Bargarh plant by 35 per cent and also set up a captive power plant.
- Tikaria facility: ACC plans to increase Tikaria unit's capacity from 1.3 million tpa to 2 million tpa.