Illustrative image – not actual.Associated Cement Cos has planned to make capital expenditure of Rs.475 crore during 2005-06, it is learnt.
Around Rs.170 crore would be spent on expanding capacity at the Lakheri plant in Rajasthan from 0.6 million tpa to 1.5 million tpa. Besides, a captive power plant of 25 MW capacity would be set up at a cost of Rs.100 crore.
Meanwhile, the expansion project at the Chaibasa plant in Jharkhand is close to completion. The project involves setting up of a 1.3 million tpa clinker plant and a 15 MW captive power plant. Grinding capacity at the Gagal plant in Himachal Pradesh is also being increased. These expansions would take ACC's total cement capacity to 20.6 million tpa.