Abhijeet Group’s coal-based power project in Banka, Bihar, is likely to face hurdles.
Abhijeet Group, engaged in power, mining, roads construction, steel, and ferro alloys businesses, created a special purpose vehicle, Jas Infrastructure Capital, to execute a coal-based power project in Banka, Bihar.
The project is involved in setting up a 1,320 MW (2x 660 MW) coal-based power unit in Phase-1 at Banka in Bihar, with a sanctioned credit limit of Rs 5,700 crore. The coal required for the project will be sourced from Mahuagarhi coal block and coal linkage.
A part of the project involving erection, procurement and construction (EPC) was awarded to Abhijeet Projects. The value of the project is worth Rs 790 crore.
To execute the project, a loan worth Rs 290 crore was taken from Canara bank and Vijaya bank. The project was accorded Environmental clearance in June 2011.
The company sublet the work, including civil, structural, architectural and external work to Kolkata-based Simplex Infrastructure. It also signed a deal with US based FJS Energy LLC for coal supply.
The project was scheduled to be completed in December 2014. However, the project was never completed, and both banks filed a complaint with the CBI in 2015.
Abhijeet Projects was required to pay a mobilisation advance of around Rs 157.9 crore in five installments, and the Simplex Infrastructure was required to give a bank guarantee to Abhijeet Projects. Both the companies have allegedly executed an amendatory agreement without the knowledge of the banks. As per the agreement, Simplex Infrastructure refunded a major portion of the mobilisation advances to Abhijeet Projects.
Abhijeet Projects has allegedly diverted the refunded amount for other purposes rather than for the said project.