Illustrative image – not actual.ABG-LDA Bulk Handling, a bulk cargo handler, achieved financial closure for the fertiliser berth project in Vishakhapatnam.
The company has achieved financial closure for the fertiliser berth project, estimated to cost Rs 310 crore. The project is being funded by a consortium of four banks headed by the SBH. It will take two years to execute the mechanised berth project which will vastly improve the operational efficiency and reduce pollution at the port, as it would obviate the need for multiple handling. The project with the capacity of six million tpa is been implemented by Vizag Agriport, a JV between ABG-LDA and IL&FS Maritime.
The project is the part of two major projects at the Visakhapatnam port. Another project is a multi-cargo mechanised berth currently under execution by the ABG. The berth with the capacity of five million tpa is estimated to cost Rs 155 crore. The facility will be handling steel, granite and other bulk cargoes. It is expected to be commissioned by December 2013.