ABB links solar project in TN with national gridIllustrative image – not actual.

Engineering firm, ABB has commissioned five substations to integrate a 648 MW solar project at Kamuthi in Tamil Nadu to the national transmission grid.

The project was awarded by independent power producer, Adani Group in 2015.

The 360 MW from the solar project is currently grid-connected, and at full capacity this facility will account for nearly 10 percent of the country's current solar potential of around seven GW.

ABB's project scope included the design, supply, installation and commissioning related to the solar plant electrification and automation systems.

The project includes two 230 kV and three 110 kV outdoor switchyards to connect to the local transmission grid, and it will enable clean power supply for around 1,50,000 households based on average national per capita consumption.

 

← All latest storiesBack to top →