Illustrative image – not actual.ABB India, power and automation technology company, has secured an order worth around Rs 178 crore from Power Grid Company of Bangladesh (PGCB).
The order was booked in the first quarter of 2017.
As part of the project, the company will construct and commission one 132 kV/33 kV air insulated switchgear substation in Kachua, and one gas insulated switchgear substation in Kalurghat, and upgrade two existing AIS substations into GIS substations in the Comilla and Modhunaghat areas.
It will also provide substation automation systems and fiber optic communications. The design, engineering, system integration, and supply of key components will be implemented in India.
Around 535 MW of transmission capacity will be added, which will power more than 2,50,000 households.
The order was booked in the first quarter of 2017.
As part of the project, the company will construct and commission one 132 kV/33 kV air insulated switchgear substation in Kachua, and one gas insulated switchgear substation in Kalurghat, and upgrade two existing AIS substations into GIS substations in the Comilla and Modhunaghat areas.
It will also provide substation automation systems and fiber optic communications. The design, engineering, system integration, and supply of key components will be implemented in India.
Around 535 MW of transmission capacity will be added, which will power more than 2,50,000 households.