Illustrative image – not actual.The Airports Authority of India (AAI) plans to undertake development and upgradation of the Visakhapatnam (Andhra Pradesh), Coimbatore (Tamil Nadu) and Kozhikode (Kerala) airports.
At the Visakhapatnam
airport, a new 10,000 feet long runway is proposed to be constructed.
Instrument Landing System and Ground Lighting facilities are also proposed to
be installed. A new integrated terminal building is also in the offing.
At the Coimbatore
airport, the new international terminal building is proposed to be
extended. Extension-cum strengthening of the runway upto 9,000 feet would be
taken up with an investment of Rs.45 crore.
The runway of the Kozhikode airport has been extended to 9,000 feet.
Besides these projects, AAI has
already commenced development of the Ahmedabad, Amritsar, Trichy, Hyderabad,
Varanasi, Lucknow, Jaipur and Guwahati airports.
At the Ahmedabad
airport, extension of the runway to 11,500 feet has been completed.
Also, the construction of a new domestic block, a taxi-way isolation bay and
extension of domestic building have been taken up with an estimated investment
of Rs.107 crore.
The runway at the Amritsar airport has been extended to 10,500 feet
at a cost of Rs.79 crore.
At the Trichy
airport, extension of the runway to a length of 7,500 feet and
construction of a terminal building complex at a cost of Rs.20 crore, has commenced.
An integrated terminal building, extension
and strengthening of the runway with an outlay of Rs.65 crore, is on the cards
at the Varanasi airport.
The runway at the Jaipur airport has been extended to 9,000 feet and
construction of a technical block-cum-control tower is in progress.