AAI to begin Phase II work of Thiruvananthapuram airport terminal soonIllustrative image – not actual.

Airports Authority of India (AAI) has decided to take up the Rs.80.58 crore second phase work of international airport at Thiruvananthapuram district of Kerala simultaneously with the Phase I work. Earlier the plan was to commence the second phase work by September 2008 and to complete it by 2010.

The work on the Rs.165 crore first phase, which includes Rs.115 crore terminal building, apron and car park, is progressing as per schedule and is scheduled for completion in December 2008. The piling work for the terminal building has been completed and the three-storied terminal building, with a floor area of 23,299 sq.m is being constructed using modern construction materials.

Of the 48.56 hectares needed for the project, the government had handed over 11.15 hectares and the second phase work will commence only after the government hands over the remaining land to AAI. The nod from the Public Investment Board (PIB) is also awaited for taking up the work for the second phase.

AAI has also initiated steps to invite tenders for the second phase work In the second phase an additional 8,000 sq.m will be added to the complex by extending the terminal on both sides. In addition, four parking bays, conveyor belts, escalators and other facilities will be set up.

Related Links:
Project profile

← All latest storiesBack to top →