Illustrative image – not actual.
In Vellore, 92 percent of the Rs 1,000-cr underground drainage (UGD) project under the Smart Cities Mission has been completed, according to Corporation Commissioner R Lakshmanan.
The remaining work includes a 650-metre pipeline bridge over the Palar river, pipe-laying in five Old Town streets, and a new pumping station near the fort in Vasanthapuram. The bridge, built 20 ft. above the riverbed, will channel sewage from 32 wards to a 50 MLD sewage treatment plant (STP) in Viruthampattu. Started in 2019, the four-phase project spans 750 km of sewer lines, 16 pumping stations, and two major STPs, covering all 60 city wards.
Key stretches like Old Bangalore Road are being re-laid, with full re-laying expected by January 2026. Around 81,000 households are currently connected, and new connections will begin in January. Critical stretches on NH-48 and near CMC are being addressed.
