82.50 MW unit of Alaknanda hydel project synchronisedIllustrative image – not actual.
The first 82.50 MW unit of Alaknanda hydel project has started operations as announced by GVK Power & Infrastructure today.

The 330 MW (4x82.50MW) Alaknanda Hydro Power Company, a step-down subsidiary of GVK, successfully synchronised its first unit with the grid on 10 April and is generating at full load.

The synchronisation of second and third units is expected this month and the last unit (fourth) is likely to be commissioned by next month.

The company is developing the 330 MW hydro project on the Alaknanda in Tehri-Pauri Garhwal districts of Uttarakhand. A power purchase agreement (PPA) has been signed with Uttar Pradesh, and 12 per cent output will be provided free to Uttarakhand.