Before the vesting order is issued by the Ministry for Coal on 23 March, the successful companies will have to furnish the performance bank guarantee that is expected to be in excess of Rs 5,000 crore.
Companies will have to furnish a performance bank guarantee equalling one year’s royalty as per the annual peak rated capacity of the block and the winning bid amount multiplied by the peak rated capacity. For example, in the non-power category, Hindalco, which won the Gare Palma IV/5 block for Rs 3,502 a tonne, will have to furnish nearly Rs 370 crore as the performance bank guarantee. This will include around Rs 18 crore as one year royalty on the annual peak rated capacity, and around Rs 350 crore as the winning bid amount multiplied by the peak rated capacity.
Similarly, Essar Power, which won the Tokisud North block for Rs 1,110 a tonne is expected to furnish nearly Rs 290 crore as the performance bank guarantee.
The estimated total benefit of royalty and e-auction amount over the entire mine life of 31 auctioned blocks will be Rs 2.09 lakh crore, according to the government.
This will assure the government meets its deadline of successfully concluding the auctions before the Ordinance lapses on 5 April, 2015.
By 20 March 2015, the government is expected to take a decision on the companies whose bids are under re-examination since outliers in the bidding pattern did not ink the agreements.