11 Mumbai flyover projects running behind scheduleIllustrative image – not actual.

The Mumbai Metropolitan Region Development Authority's (MMRDA), 11 major flyover projects, totaling Rs.242 crore on the eastern and western express highways are unlikely to be completed as per the schedule, due to various reasons. Except for a couple of projects nearing completion, work on others is only halfway through.

The projects were inaugurated in 2006 and were likely to be completed in June 2009. However, now the projects might get delayed up to January 2010.

The flyover at the Bharatmata Junction on the Eastern Express Highway has been delayed by three more months due to shifting of utility services. The bridge is being built at a cost of Rs.15.83 crore.

Four other flyovers on Dr Ambedkar Road, including the Sion Hospital flyover which is being built at a cost Rs. 20.70 crore and at Hindmata junction, are also behind schedule. Another delayed project is the bridge between Tulpule Chowk and King's Circle, estimated to cost Rs.46.26 crore. The flyovers at Suman Nagar, Chembur and Navgarh Junction in Mulund will be opened to traffic by July 2009.

However, Western Express Highway projects are on a faster track. Work on the Dindoshi junction flyover at Goregaon has already been completed. Other flyovers on this highway, including one at airport junction in Ville Parle being built at a cost of Rs. 33 crore and another in Kandivali near Thakur Complex being built at a cost of Rs. 31 crore will be over by January 2009.

The MMRDA has extended the deadline for the Rs. 28 crore Barfiwala lane flyover at Andheri and another at the Times of India junction at Malad to December 2009.

Even if the MMRDA is trying to operationalise these flyovers by early 2009, it may take the entire year before they are actually opened to traffic.