Shree Geeta Textile Mills setting up unit in MP Illustrative image – not actual.

Shree Geeta Textile Mills is setting up a cotton yarn unit at Bodarli, in Burhanpur district of Madhya Pradesh.


The project will also include a cotton fabrics unit with a capacity of 2,500 tonne per annum, and a synthetic fabrics unit with a capacity of 1,300 tonne per annum.


The company informed ProjectsToday that the project would spread over 79 acre of land and would be set up with an investment of Rs 65 crore. Around Rs 47 crore of the project cost will be funded through bank loan and the remaining Rs 18 crore from internal accruals. The company is in the process of achieving financial closure.


Shree Geeta Textile Mills has appointed Mittal Construction Unit as the civil contractor, and Lakshmi Machine Works and Saurer Schlafhorst as machinery suppliers for the project.


Work on the project is underway with completion scheduled for April 2015.

 

More Project Info:
Cotton yarn (Bodarli) project

← All latest storiesBack to top →