RIL starts gas production from new well in KG-D6 Illustrative image – not actual.

Reliance Industries (RIL) has started production at the MA-8 well in KG-D6 block to augment output from the block.

 

The production has started to ramp up output from the KG-D6 block to about 13.7 million standard cu mtr per day.

 

In December 2013, RIL and its partners, BP Plc of UK and Canada's Niko Resources had spud the seventh well on the MA oil and gas field in the KG-DWN-98/3 or KG-D6 block in the Krishna Godavari basin.

 

Currently, MA-8 is in the process of stabilisation and is producing less than 1.5 million standard cu mtr per day. The well is projected to go upto 2.5 million standard cu mtr per day.

 

The current output of 13.7 million standard cu mtr per day in KG-D6 block is made up of about 8.7 million standard cu mtr per day from Dhirubhai 1 and 3 (D1&D3) gas field and about five million standard cu mtr per day from the MA field in the same block.