Neyveli’s TPS-II expansion project to be commissioned soonIllustrative image – not actual.
Neyveli Lignite Corporation (NLC) is expected to commission Unit-I of its 500 (2x250) MW TPS-II expansion project this month.


Though the rectification works in Unit-I had been completed in February, it could not attain stabilised operation till date, due to the recurring technical problem of the super heater coil in fluidised bed heat exchangers.

Unit-II of the coal-based power project is likely to be commissioned in October 2014.


Another 2x500 MW project, Neyveli New Thermal Power Plant (NNTPP), is also making progress with contracts for three major packages worth Rs 4,751 crore being awarded. Unit-I of the project is expected to be commissioned in October 2017 and Unit-II in April 2018.


NLC, which entered the renewable energy sector last year, has stated that the erection activities of the 51 MW wind project at Tirunelveli in Tamil Nadu is going well and the commissioning of the first three sets of wind turbo generators is  expected by the month end. The rest will be commissioned by October 2014. For its maiden 10 MW solar power plant at Neyveli, orders have been placed with BHEL.


NLC plans to add 2,500 MW in the next three years.


 