Bangalore Metro Phase-I to be completed in September 2015Illustrative image – not actual.

Phase-I of the Bangalore Metro Rail project, which was expected to be completed by March 2015, is now likely to be completed by September, 2015. 


The 42.3 km Phase-I is being developed by Bangalore Metro Rail Corporation (BMRCL).


The corporation is expected to extend Reach 3 and Reach 3 A that is operational till Peenya, upto Hesaraghatta Main Road by November 2014, and the distance of 6.52 km between Magadi Road to Mysore Road is likely to be completed by December 2014.


So far, BMRCL has completed only 17 km of the 42.3 km in Phase-I. Earlier this year, the company had opened a 10.30 km stretch of the metro rail with 10 stations on reach 3 of the project, from Peenya to Swastik Circle in north Bangalore for commercial operations, to add to the 6.7 km in east Bangalore that opened in October 2011.


Due to delay in completion of the project, the cost of Phase-I has escalated  from Rs 11,600 crore to Rs 13,800 crore.


Further, the company is also planning to float a tender for Phase-II of the metro rail project by July, 2014. The 72 km Phase-II entails an investment of Rs 26,405.14 crore and it has already obtained approval from the central government.

 