Illustrative image – not actual.The Tamil Nadu Highways Department is executing Phase-III of the ring road project linking Kangeyam road with Chennimalai road.
The department has started off by laying roads on land portions in Pudur Pudupalayam village where compensation has been awarded.
The acquisition process could not be completed in Erode C village where there were as many as 24 petitioners. However, the judgment on land acquisition has been delivered in favour of the government. Similar developments are expected in three other villages: Muthampalayam, Thindal and Vadamugavellode.
In Phase-III and Phase-IV, which will be executed simultaneously, the ring road will be extended to a length of seven km from Kangeyam road to Thindal. The project involving construction of a bridge at Jeeva Nagar will be completed by February-March 2017.
A stretch of 7.6 km, laid in the first two phases from Kokkarayanpettai in Namakkal district to Kangeyam road, is already being utilised by the travelling public.