Illustrative image – not actual.Odisha Power Transmission Corporation (OPTCL) is planning to lay underground power cables replacing the existing electric poles in the state.
The project will be executed in various phases. In Phase-I of the project, four major roads of around 50 km, will be included. The project is part of the State Capital Region Improvement of Power Supply (Scrips) project for which the government will invest around Rs 1,500 crore in phases.
OPTCL will implement the project in consultation with the Central Electricity Supply Utility (Cesu). While the Cesu is preparing the detailed project report (DPR) for the project, OPTCL will execute the work. The DPR is expected to be prepared by the end of June 2014 and from August work will get rolling.
The average cost of the underground cabling work will vary from Rs one crore to Rs 1.5 crore for a one km stretch. In case of more service lines joining the main supply line on the road, the underground cabling will cost more. But in case of less density of electrical poles on the service lanes, the cost will be less.