Illustrative image – not actual.State-owned ONGC has approached the Ministry of Environment and Forests (MoEF) seeking the green nod for drilling 45 development wells and other related infrastructure in the Krishna-Godavari basin.
The cost of this work is over Rs 53,000 crore. The block KG-DWN-98/2 or KG-D5 is divided into two parts -- Northern Development Area (NDA) and Southern Development Area (SDA). The NDA, which is deep waters, has a depth of upto 1,800 mtr; while SDA which has ultra-deep waters, has a depth upto 3,100 mtr.
The present proposal is for development in the Northern Development Area (NDA). ONGC is slated to start the production in 2019. It will have a peak output of 4.5 million tonne a year, which will be 20 per cent more than previous estimates.
The Krishna Godavari basin block KG-DWN-98/2, or KG-D5, will first see large oil production from the east coast, which has 10 gas discoveries. KG-D5 sits next to Reliance Industries' producing KG-DWN-98/3 or KG-D6 area.