Illustrative image – not actual.
NTPC is setting up a new project with two units of 660 MW each, at Bilhaur in Kanpur, which will help the state get at least 50 per cent power from it. About 1,200 acre of land is required for the Bilhaur project. The first unit is likely to become operational by 2022.
Another NTPC project -- Stage-II at Tanda -- in Ambedkarnagar, will also help UP get 832 MW power. Under it, two units of 660 MW will be set up. The state government will provide assistance for acquiring 800 acre of land for this project.
The 2x660 MW units at Meja thermal power project in Allahabad is also under construction. The project is a joint venture of NTPC and UP Rajya Vidyut Utpadan Nigam.
Under Unchahar Stage-IV project, NTPC has land available, and construction for one unit of 500 MW is on.
NTPC projects with a capacity of 3,648 MW are also under construction in the northern region of the state. Overall, UP has been allocated 1,921 MW from these projects. The first share of 1,657 MW power will be available by 2016-17.
A small hydro project of 2x4 MW at Singrauli is likely to be commissioned in July-August this year. Besides, a 500 MW project at Vindhyachal might be commissioned by end 2015.
More Project Info:
Coal Based Power (Meja) Project
Tanda Coal Based Power Project - Stage II
Feroze Gandhi Unchahar Power Project (Stage-IV)