Illustrative image – not actual.The Mumbai Metropolitan Region Development Authority (MMRDA) has begun the land acquisition process for the proposed Virar-Alibaug Multi-Modal Corridor (MMC), in Mumbai, but is confused over which land acquisition act to adopt for the project.
The Authority has started the documentation process with the Urban Development Department for acquisition of 1,250 ha of land required to execute the project. But, MMRDA is in a state of confusion over which land acquisition act will be amended; the one which was put in force in 2008 or the newly adopted law which came into effect on 1 January, 2014.
The state government in 2008 had amended the Land Acquisition Act, 1894, when the project was first conceptualised. On the other hand, the union government in January 2014 brought into effect the new Land Acquisition Act, 2013.
The MMRDA has referred the issue for legal opinion, in order to get a clear picture of which law will be amended for the project. The estimated cost of the land acquisition is about Rs 1,838 crore.
Inspite of facing legal hurdles, MMRDA has already started focusing on the development of growth centres, and the first centre will be developed in Kalyan. The MMRDA has proposed to set up seven growth centres at Virar, Bhiwandi, Kalyan, Dombivli, Panvel, Taloja and Uran.
Work has also begun to widen roads in the Mumbai Metropolitan Region at the Bhivpuri-Karjat belt, which will eventually help in connecting the multi-modal Corridor.
The project involves development of the 126 km Virar-Alibaug multi-modal corridor (MMC) in Maharashtra, at a total cost of Rs 12,975 crore. The MMC will be implemented in two phases.