It has successfully achieved boiler light-up of the first unit of 660 MW and is scheduled to be synchronised to the grid in November 2014.
The second and third units of the project will begin to generate electricity in November 2014 and April 2015, respectively. The second unit synchronisation is likely to take place in March 2015.
By 2015, this power project will be able to generate 1,320 MW. The third unit will be completely operational in FY16.
At present, MAHAGENCO has an installed capacity of 10,737 MW out of which 7,480 MW is from thermal.
The addition of the three 660 MW units will increase the total installed capacity of thermal power to 9,460 MW.